Shawton Engineering Ltd v. DGP International Ltd (t/a Design Group Partners)
Reference: [2005] EWCA Civ 1359; LTL 18/11/2005
Court: Court of Appeal
Comment:
Where a subcontract that required works to be completed by fixed dates had been varied, the work had to be completed within a reasonable time. The contractor had failed to establish what was a reasonable time for completion of the works. Therefore the subcontractor was not in breach of contract by reason of delay and a letter from the contractor could not have made time of the essence.